Current Road Work Alerts

 

HAMILTON COUNTY U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mtn. Blvd.):

Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  The Manufacturers Road entrance ramp onto US‑27 North has been closed until spring 2013 to allow for construction of several retaining walls and portions of the new bridges over the railroad and Manning Street.  Detours are posted.  The Manning Street and Whitehall Road exit ramps from U.S. 27 North have both been permanently closed.  During nighttime work, at least one lane will remain open in each direction.  On Tuesday, October 16 Elmwood Drive will be closed from 6PM-6AM between East Frontage Road and Whitehall Road to allow the contractor to perform a bridge deck pour.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is October 2014.

HAMILTON COUNTY, I-24 resurfacing beginning at the Georgia State Line (LM 0.0/MM 171) to the bridge over Chattanooga Creek (LM 6.18/MM 177) including bridge deck repair:

Paving and bridge repair work are complete.  There will be no lane closures during this report period.  Estimated project completion date is October 2012.

HAMILTON COUNTY, Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:

The contractor will be laying pipe across the roadway at several locations.  This work will be performed during the day on weekdays only.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is September 2013.

HAMILTON COUNTY, SR-60 construction of concrete slab bridge over branch (LM 0.44):

(This project is near the Meigs County Line.)  The contractor may be performing work throughout the project area between 7AM-6PM Monday through Saturday.  Flaggers will assist with traffic control.  Estimated project completion date is November 2012.

HAMILTON COUNTY, Shallowford Road construction of concrete Bulb-Tee beam bridge over South Chickamauga Creek (LM 4.01), including grading drainage, and paving:

During this report period the contractor will be performing paving operations.  There will be no long-term lane closures as a result of this project.  The contractor may have intermittent short-term lane closures to perform bridge work during non-peak hours.  Flaggers will assist with traffic control as needed.  Estimated project completion date is October 2012.

HAMILTON COUNTY, U.S. 11 (SR-2, Lee Highway) construction of a concrete box beam bridge over the CSX Railroad (LM 16.25), including grading, drainage and paving:

During this report period, the contractor will be working on addressing punchlist items.  At least one lane of traffic in each direction will be open at all times.  Flaggers will assist with traffic control as needed.  Estimated project completion date is October 2012.

HAMILTON COUNTY, Daugherty Ferry Road construction of a concrete box beam bridge, including grading, drainage and paving, over Sale Creek (LM 0.79):

The project to replace the truss bridge over Sale Creek is underway, and the contractor has closed Daugherty Ferry Road to traffic at the bridge for the duration of the project. The detour route using Coulterville Road and Elesea Road will be clearly marked. Estimated project completion date is November 2012.

BRADLEY COUNTY, SR-60 (Dalton Pike) road widening from near Gilliland Road to U.S. 64 (SR-311):

SR-60 (Dalton Pike) is undergoing major reconstruction.  The existing two-lane highway is being widened to a five-lane highway with sidewalk, curb and gutter on either side.  All driveways and side streets along the 2.7‑mile project are being lowered or raised to match the proposed SR-60 grade.  Delays are to be expected at the intersection of Dalton Pike and McGrady Drive/Treasury Drive as the contractor works to upgrade the intersection.  Hawk Street (east) was closed off to through traffic on July 9, 2012 and will not be opened until September 14, 2012.  The temporary road closure is necessary to excavate and build a box culvert across the proposed new alignment.  The contractor will be installing drainage pipe, box culvert, sidewalk, curb and gutter in the coming weeks.  Detour signs and message boards will be provided to assist motorists.  Estimated project completion date is Late Fall 2012.

BRADLEY COUNTY, SR-60 construction of two concrete box bridges over Greasy Creek (LM 21.02) and Branch Creek (LM 24.28) including grading, drainage and paving:

The majority of the work is completed on this project.  Minimal interruptions are expected.  Flaggers will assist with traffic control as needed.  Estimated project completion date is October 2012.

BRADLEY and POLK COUNTIES, SR-74 (GA225/Spring Place Road)between the Tennessee/Georgia State Line and SR-313 (Ladd Springs Road) construction of two concrete box bridges over the Conasauga River Overflow (LM 0.01) and the Conasauga River (LM 0.14) including grading, drainage and paving:

SR-74 (GA225/Spring Place Road) is closed to traffic for the duration of the project to replace two bridges between the GA/TN state line and MM 0.45.  There are detour signs and message boards posted in GA and TN to assist motorists, and major delays are expected.  Local traffic will be permitted, at all times, to access businesses and residential property within road closure area.  However traffic will not be permitted to enter the active work area that is adjacent to the Conasauga River bridges.  Every effort will be made to minimize the inconvenience to motorists, businesses, residences, and property owners.  TDOT and consultant staff will be available throughout the project to address any questions or concerns.  Estimated project completion date is October 2013.

BRADLEY COUNTY, State Industrial Access road serving Wacker Chemical Company, including grading, drainage and paving:

During this report period, the contractor will be working on the Lauderdale Road tie-in to the new road.  Sometime during the report period the road will be opened, if weather conditions are favorable.  A detour is in effect on the Lower River Road.  Please follow the detour signs and highway markings through the detour.  Estimated project completion date is December 2012.